Buried Risk: A Guide to Differing Site Conditions Claims Under FAR 52.236-2
This article was researched and written by Ask Pub K, drawing on Pub K's curated library of authoritative GovCon documents. It has been lightly edited by Pub K's editors for accuracy and clarity.

Every construction contractor has had that moment on site: the boring logs said one thing, the backhoe found another, and the budget just changed. Federal construction law has a clause for exactly that moment — and knowing which of its two flavors applies can be the difference between a six-figure equitable adjustment and a denied claim.
The Differing Site Conditions (DSC) clause, found at FAR 52.236-2, is standard in fixed-price federal construction contracts above the simplified acquisition threshold.[1] It shifts the risk of certain unanticipated subsurface or latent conditions from the contractor to the government, reducing the padding contractors would otherwise build into bids to cover the unknown.[2] The clause creates two distinct causes of action — Type I and Type II — and contractors routinely plead both, because each covers a different failure of expectation.
Type I: The Contract Said One Thing, the Ground Said Another
A Type I DSC claim alleges that the contract documents affirmatively represented a site condition, and reality did not match. To prevail, a contractor generally must show: (1) the contract contained a positive indication of the conditions at the site; (2) the contractor reasonably interpreted and relied on that indication; (3) the conditions actually encountered materially differed from those indicated; (4) the conditions were reasonably unforeseeable; and (5) the contractor suffered damages as a result.[3] The clause typically operates through boring logs, geotechnical reports, or drawings — if those materials say nothing about the condition at issue, there is no “indication” to rely on, and the claim fails at the threshold.[4]
Type II: Nobody Said Anything — But No One Expected This Either
Type II is the clause’s catch-all, and the harder claim to win. It does not require the contract to address the condition. Instead, a contractor must show the condition was unusual, materially different from what would ordinarily be encountered in similar work in the area, and unknown and unforeseeable despite reasonable site investigation.[5] Because there is no contractual baseline to point to, Type II claims typically turn on expert and historical evidence of what is “usual” for the region and the type of work — a fact-intensive and often expensive showing.[6]
The Conditions Attached to Both
Both claims carry conditions that are easy to overlook. Notice must be given to the contracting officer promptly and before the condition is disturbed, though boards routinely excuse strict non-compliance absent actual prejudice to the government.[7] No equitable adjustment will be allowed for a request made after final payment.[8] And weather or acts of God, standing alone, are not DSCs — though weather that reveals a previously unknown and genuine site defect can still support a claim.[9]
Why the Distinction Matters
Boards and the Court of Federal Claims deny far more DSC claims than they grant, usually because a contractor conflates the two theories or fails a single element — the site information was too ambiguous to “indicate” anything, or the condition, while bad luck, was not actually unusual for the region.[10] Treating Type I and Type II as a single undifferentiated “surprise in the dirt” claim is the most common drafting in equitable adjustment requests — and it is entirely avoidable with careful, element-by-element pleading.
1. FAR 52.236-2, Differing Site Conditions; FAR 36.502 (clause prescription). acquisition.gov/far/52.236-2 ↩
2. Pub K, Don’t Know, Know: FAR 52.236-2 Differing Site Conditions. pubkgroup.com ↩
3. Pub K, No Constructive Change When the Agency Did Not Unequivocally Direct Contractor to Alter Performance (Appeals of David Boland, Inc., ASBCA Nos. 61923, 61924, 61925). pubkgroup.com ↩
4. Pub K, You May Have Encountered Unexpected Conditions, But That Doesn’t Make Them “Differing Site Conditions”. pubkgroup.com ↩
5. Pub K, No Constructive Change… (Boland), supra. pubkgroup.com ↩
6. Pub K, Don’t Know, Know: FAR 52.236-2 Differing Site Conditions. pubkgroup.com ↩
7. Pub K, Don’t Know, Know: FAR 52.236-2 Differing Site Conditions (notice requirement). pubkgroup.com ↩
8. Pub K, Don’t Know, Know: FAR 52.236-2 Differing Site Conditions (equitable adjustment barred after final payment). pubkgroup.com ↩
9. Pub K, Don’t Know, Know: FAR 52.236-2 Differing Site Conditions (weather and acts of God). pubkgroup.com ↩
10. Pub K, Why Did This Contractor’s Differing Site Condition Claim Fall Apart? (Kloepfer, Inc. v. Department of Transportation, CBCA 7456). pubkgroup.com ↩