Articles

🔒 Members Only · Protests & Claims BriefYou’ve reached the member portion of this brief.Members read the full analysis and the source documents in every Brief, six days a week.
Agency Not Required to Settle for “Adequate” Office Space; GAO B-414207, Vanguard Building LP
Costs Recommended Where Agency Cannot Provide Documentation Supporting its Price Realism Analysis; GAO B-413444.3, Hewlett Packard Enterprise Company–Costs
Agency Can Reasonably Conclude Technical Approach has Merit, While Rejecting Proposed Cost Savings; GAO B-412990.3, Glacier Technical Solutions, LLC
Protester Should Have Resolved Questions About Requirement Prior to Deadline for Receipt of Revised Proposals; GAO B-413320, Wall Colmonoy Corporation
Agency’s Award of Intergovernmental Support Agreement Subject to GAO Jurisdiction; GAO B-414367, Red River Waste Solutions Inc.
DCAA Verification of Protester’s Accounting System a Material Requirement and Cannot be Waived; GAO B-413104.9, Leader Communications Inc.
Agency Not Required to Include Price of Relocation in Its Analysis of Lease Costs Where Costs for Moving or Remaining in Current Location Are About the Same; GAO B-413513.2, LCPP LLC
Area Office May Assume Shared Interests Among Family Members, and Appellant Must Provide Evidence Rebutting this Assumption; SBA No. SIZ-5809, Size Appeal of CTSI-FM, LLC
Contractor Fails to Meet Size Standard by Assigning Subcontractor to Manufacture End Item; SBA No. SIZ-581, Technology Associates Inc.
Discovery Required Before Contractor’s Fifth Amendment Taking Claim Can Be Determined; COFC No. 15-378C, Global Freight Systems Co. W.L.L. v. United States
Error in Considering Contractor’s Financial Situation Does Not Derail Termination for Default; ASBCA No. 59153, Appeal of Delfasco LLC
Contractor’s Accounting of Building Lease Costs Not a Violation of CAS 404; ASBCA 60131, Appeal of Exelis Inc.
Finding of Affiliation Erroneous Where Appellant is Not Controlled by Firm With Which it Has Subcontract Relationships; SBA No. SIZ-5818, Size Appeal of INV Technologies Inc.
Receipt of Electronic Quotation by Government Server Not Equivalent to Being Under Government Control; GAO B-413557.3, Peers Health
Appeal is Timely When Government Cannot Prove the Date Contractor Received Final Decision; ASBCA No. 60308, Appeal of Military Aircraft Parts
CBCA Can Review Claims Based on Negative CPARs But Cannot Direct Agency to Take Specific Actions; CBCA 5516, CompuCraft Inc. v. General Services Administration
Contractor Waived Its Right to Recovery by Signing Release of Claims During Dispute; PSBCA No. 6625, MBD Maintenance LLC
Request for Information to Determine Responsibility Does Not Amount to Discussions; GAO B-412278.6, Northrop Grumman Systems Corporation—Costs
Kingdomware Decision that a Task Order is a Contract Does Not Disturb SBA’s Regulations for Determining Timeliness of Size Protests; SBA No. SIZ-5800, Size Appeal of Platinum Business Services, LLC re: Redhorse Corporation