Just Because Protester’s Reading of Solicitation Differed From Agency’s Does Not Mean Solicitation Was Ambiguous; Salient Federal-SGIS, Inc. v. United States, COFC No. 20-1416C
Protester’s Challenge to Evaluation Really Just a Disagreement With Agency’s Assessment; KARL STORZ Endoscopy-America, Inc., GAO B-419404, B-419404.2
Protester Alleges Unstated Criterion, But GAO Finds Solicitation Clearly Set Forth the Requirement; Hurricane Consulting Inc., GAO B-418638.2
Agency Not Required to Include Past Performance Evaluation Factor in Solicitation; Pathfinder Consultants, LLC, GAO B-419509
Court Nixes Sole-Source Bridge Contract; AGMA Security Service, Inc. v. United States, COFC No. 21-740C
Protester Not An Interested Party to Challenge Alleged Waiver/Relaxation of a Solicitation Requirement; CACI, Inc.-Federal, GAO B-419499
GAO Finds Protester Effectively Conceded Deficiencies Assessed to Its Proposal, Dismisses Protest; Mesotech International, Inc, GAO B-419534
Agency Reasonably Rejected Proposal Due to “Generic and Aspirational” Management Approach that Lacked Detail; Lamb Informatics, Ltd., GAO B-418405.5, B-418405.6
Protester Not Entitled to Costs for Any of Its Four Related Protests; Apex Transit Solutions, LLC—Costs, GAO B-418631.4
Untimely Agency Protest Dooms Subsequent GAO Protest; Rotair Aerospace Corporation, GAO B-419570
GAO Finds that Protest Is Essentially an Untimely Request for Reconsideration; VS2, LLC, GAO B-418942.2, B-418942.5
Protester Not Prejudiced by Agency’s Waiver of Material Solicitation Requirement; Gemini Tech Services, Inc., GAO B-418233.5, B-418233.6
Protester’s Proposed Personnel Greatly Exceeded RFP’s Experience and Education Requirements, But Agency Found them Overqualified; ICF Incorporated, L.L.C., B-419049.3, B-419049.4
Court Rejects Bait-and-Switch Allegation Because Argument Was Premised on Conjecture; The Severson Group, LLP v. United States, COFC No. 20-1887
GAO Finds that Protester Misinterpreted the Meaning of “Gloves”; Global-PPE, Inc., GAO B-419536
Proposal Undone by Protester’s Failure to Identify Deficiencies in the Agency’s Project Design; BB Governmental Services Srl, GAO B-419205.3
Agency Made an Improper Upward Adjustment to Contractor’s Probable Costs; Vectrus Mission Solutions Corporation; Vanquish Worldwide, LLC, GAO B-418942 et al.
Protester Unable to Prove that Awardee’s Staffing Approach is Unacceptable; ISS Action, Inc., GAO B-419469
Quotation Was Unacceptable Because It Proposed an Item that Had Been Removed from the Protester’s FSS Contract; Chicago American Manufacturing, LLC, GAO B-419242